Design and delivery of fly ash grout into a inflated bag 5m x 5m x 3.5m to rebuild a pillar at cut though 33 that was mined but needed to be reinstated for pillar safety factor. To deliver this pillar replacement Tim organised a grout bag, a 305m borehole and 400m3 of grout and underground supervision.